A gate with delay 70 ps has inputs arriving at 120 and 180 ps. When does its output arrive?
Write units the way you normally would: 1.5 ps and 0.0015 ns are the same answer.
Check
A net feeds two gates: one of delay 90 ps whose output is required by 400 ps, and one of delay 60 ps required by 520 ps. When is the net required?
Write units the way you normally would: 1.5 ps and 0.0015 ns are the same answer.
Check
A net arrives at 420 ps, and the longest path from it to an output takes 120 ps more. With a 500 ps clock, what's its slack?
Write units the way you normally would: 1.5 ps and 0.0015 ns are the same answer.