S10 Power system analysis · Practice
Optimal power flow and locational prices
Problems dealt one at a time, with new numbers every time. The kinds you miss come back more often, and you can keep going as long as you like.
0 solved
0 in a row
0 of 10 kinds solid
Check
A cheap generator at A sends power over a line rated 150 MW to a 450 MW load at B, where a costlier generator also sits. How much must B's generator produce?
Write units the way you normally would: 1.5 MW, 1500 kW and 0.0015 GW are the same answer.
Check
A congested line carries 300 MW from a bus priced at 12 to one priced at 30 dollars per MWh. What's its congestion rent, in dollars per hour?
Check
A 550 MW load at B is served by a 10 dollars per MWh generator at A through a 300 MW line and by a 30 dollars per MWh generator at B. What's the total cost per hour?
Check
A triangle of identical lines has generators at buses 1 and 2 and a 300 MW load at bus 3, with line 1–3 limited to 110 MW. What's the most bus 1's generator can produce?
Write units the way you normally would: 1.5 MW, 1500 kW and 0.0015 GW are the same answer.
Check
In the same triangle, with line 1–3 binding, generator 1 costs 20 and generator 2 costs 35 dollars per MWh. What's the LMP at bus 3?
Check
A unit costs 20000 dollars to start and 800 dollars per hour to keep running at minimum output when it isn't needed. Above what idle gap is shutting it down cheaper?
Check
An uncongested line carries 600 MW from a generator priced at 20 dollars per MWh, with losses , B = 5 × 10⁻⁵ per MW.
(a)
What is the marginal loss factor?
(b)
What is the LMP at the receiving bus?
Check
Congestion rent (dollars per hour): 400 MW from 8 to 25 dollars per MWh?
Check
Bus-3 LMP in the binding triangle, costs 10 and 40?
Check
Breakeven idle time: start cost 3000, no-load cost 500 per hour?
A kind of problem counts as solid once you've got it right on the first try twice in a row. Back to the lesson · Practice every topic in S10