S10 · Problem set 12
Problem set 12: area control error, interconnection frequency response, inertia and ROCOF, state estimation, contingency flows, transfer distribution, dynamic ratings, phase shifters, marginal prices, reliability indices, solar on feeders, harmonics and HVDC converters
These problems follow a system operator's day: frequency and interchange, the estimator's picture of the network, the security checks that keep it safe after any single outage, the market that prices every bus, and the distribution feeders, harmonics and converters at its edges.
Check
An area's tie-line flow is 50 MW from schedule, frequency is −0.04 Hz from 60, and its bias is −400 MW/0.1 Hz.
(a)
What is its area control error?
Write units the way you normally would: 1.5 MW, 1500 kW and 0.0015 GW are the same answer.
Check
An interconnection of 50 GW (all generation at droop 0.04, load damping D = 1.5) loses 2.5 GW.
(a)
Where does its frequency settle, relative to 60 Hz?
Write units the way you normally would: 1.5 Hz, 1500 mHz and 0.0015 kHz are the same answer.
(b)
What is its frequency response, in MW per 0.1 Hz (negative)?
Check
A 40 GW system's synchronous units have H = 4 s, and 0.6 of its generation is inverter-based without inertia. It loses 3 GW.
(a)
What is the initial ROCOF?
Write units the way you normally would: 1.5 Hz/s, 1500 mHz/s and 0.0015 kHz/s are the same answer.
Check
Two meters on one flow read 0.95 pu (σ = 0.01) and 1.12 pu (σ = 0.05).
(a)
What is the WLS estimate?
(b)
What is the normalized difference between the readings (above 3 suggests bad data)?
Check
A monitored line carries 0.4 pu; line k carries 0.6 pu. For a transfer between line k's ends, line k itself takes 0.6 and the monitored line 0.35.
(a)
What is the outage distribution factor?
(b)
What does the monitored line carry if line k trips?
Check
A line's PTDF for a 100 MW transaction is 0.25; it already carries 500 MW against a 600 MW rating.
(a)
What will it carry with the transaction?
Write units the way you normally would: 1.5 MW, 1500 kW and 0.0015 GW are the same answer.
(b)
What's the largest such transaction its rating allows?
Check
A line rated 800 A at static conditions sheds 45 W/m by convection, 15 W/m by radiation and absorbs 14 W/m of sun. Measured wind raises convection 2.5 times.
(a)
What is its dynamic rating?
Write units the way you normally would: 1.5 A, 1500 mA and 0.0015 kA are the same answer.
Check
A 2 pu transfer splits between path A (x = 0.05 pu, rated 1 pu) and path B (x = 0.15 pu). A phase shifter on A may be used.
(a)
What does A carry naturally?
(b)
What phase shift (negative relieves A) brings A to its rating, if it's over?
Check
A remote generator priced 20 dollars per MWh sends 400 MW with losses (B = 0.0001 per MW) to a bus where congestion adds 15 dollars per MWh.
(a)
What is the receiving bus's LMP?
Check
A utility serving 20000 customers had 15000 customer interruptions in a year, averaging 120 minutes each.
(a)
What is its SAIFI?
(b)
What is its SAIDI?
Check
Inverters export 4 MW and absorb 1.5 Mvar at the end of a 12.47 kV feeder of 1 + j2 Ω.
(a)
How much do they change the voltage there?
(b)
How many vars would cancel the rise completely?
Write units the way you normally would: 1.5 Mvar, 1500 kvar and 0.0015 Gvar are the same answer.
Check
Each phase of a balanced four-wire load draws 50 A of fundamental, 10 A of third harmonic and 15 A of fifth.
(a)
What is each phase's current THD?
(b)
What flows in the neutral?
Write units the way you normally would: 1.5 A, 1500 mA and 0.0015 kA are the same answer.
Check
A rectifier's valve-side line voltage is 200 kV RMS; it fires at α = 10° and carries 3 kA through a commutating reactance of 15 Ω.
(a)
What is its DC voltage?
Write units the way you normally would: 1.5 kV, 1500 V and 0.0015 MV are the same answer.
(b)
What power does it deliver?
Check
Why does a system operator run contingency analysis continuously rather than only when a line trips?
Have paper and a calculator ready. Work each problem out by hand, then enter the answer. Your first try on each one counts toward your score.
Practice
Keep practicing
13 kinds of problem on this topic, dealt one at a time with new numbers every time, for as long as you like.