S10 Power system analysis · Practice
Generation adequacy and reliability
Problems dealt one at a time, with new numbers every time. The kinds you miss come back more often, and you can keep going as long as you like.
0 solved
0 in a row
0 of 9 kinds solid
Check
A system has 6 identical units, each with forced outage rate 0.02.
(a)
What's the probability all are available?
(b)
That exactly one is out?
(c)
That two or more are out?
Check
Five 100 MW units (FOR 0.05) serve a daily peak of 310 MW on 250 days a year, and much lighter loads otherwise.
(a)
What's the loss-of-load probability on a peak day?
(b)
What LOLE do the peak days contribute per year?
Check
A system has 1200 MW installed for a peak of 1091 MW.
(a)
What is its reserve margin?
Check
A 100 MW unit (FOR 0.05) and a 150 MW unit (FOR 0.08) make up a system.
(a)
What's the probability of no capacity out?
(b)
Of everything out?
(c)
Of exactly one unit out (either)?
Check
A system's LOLE is 2 days per year, and each loss-of-load day averages 4 hours of shortfall.
(a)
By what factor must its risk fall to meet one day in ten years?
(b)
About how many loss-of-load hours per year is that?
Check
A 200 MW wind farm adds the same reliability as 15% of its nameplate in perfectly reliable capacity.
(a)
What is its capacity credit?
Write units the way you normally would: 1.5 MW, 1500 kW and 0.0015 GW are the same answer.
Check
Probability exactly one of 3 units (FOR 0.04) is out?
Check
Reserve margin: 900 MW for a 750 MW peak?
Check
LOLE from 60 days at daily LOLP 0.001?
A kind of problem counts as solid once you've got it right on the first try twice in a row. Back to the lesson · Practice every topic in S10